TSMC is about to lose one of its biggest advantages - cheap, grid-based power, as a new energy law set to pass in Taiwan is going to cause a massive headache for the world's best semiconductor manufacturer.

The Taiwanese government is pushing an amendment to the Energy Management Law, which requires all large commercial electricity users to generate and store their own power, excluding only schools and hospitals. As one of the island's largest energy consumers, TSMC will now have to work out how it's going to generate approximately 9% of Taiwan's electricity over the course of a year, as that is how much the company used over the course of 2024.
Popular Now: Ayaneo has officially brought high-end gaming PC pricing to handheldsTSMC's energy use has already grown 10 - 20% annually for the past four years, and industry forecasts suggest it could consume 24% of Taiwan's total electricity by 2030. Meanwhile, the island's electricity supply has struggled to keep pace with demand from expanding electronics manufacturing facilities and fabrication plants. This discrepancy is now threatening to stifle the growth of not just TSMC, but the broader semiconductor industry, and is putting strain on vital services across Taiwan such as schools and hospitals.
To free up some energy usage for other purposes, the amendment will require any commercial entity that consumes an electricity load of more than 5MW to generate and store its own power, effectively severing its connection to Taiwan's electricity grid.

Frequently Asked Questions
TweakBot answers common questions about this news using TweakTown's own coverage from this page and related content from our archive. Tap a question to reveal the answer, or type your own below.
What exemptions to the new law does the article mention?
What is the industry forecast for TSMC’s share of Taiwan’s electricity consumption by 2030?
How might the amendment affect TSMC’s connection to Taiwan’s grid and its operational planning?
What broader impacts on Taiwan’s services and semiconductor growth does the article highlight as related to the electricity shortfall?
Have a question not listed here? Ask below and TweakBot will answer it.
The company has signed long-term agreements to source renewable energy, including wind power. But as the new law moves toward passage, the pressure to balance energy costs, the expected growth of the company, and the production of the cutting-edge semiconductors will undoubtedly become quite difficult.